Design and selections: 4 to 8 weeks
Measuring, layout options, 3D renderings and choosing cabinets, counters, tile, fixtures and lighting. Making decisions promptly keeps this phase short.
Ordering and permits: 3 to 8 weeks
Cabinet lead times are usually the longest wait. Permits are submitted during this time so construction can start when materials are ready.
Construction: 6 to 10 weeks
- Protection and demolition
- Framing, plumbing and electrical rough-in, then inspection
- Drywall, flooring and paint
- Cabinet installation
- Countertop templating and installation, usually one to two weeks after cabinets
- Backsplash, fixtures, appliances and trim
- Final inspection and punch list
What can stretch the timeline
Layout changes, structural work, hidden damage in older homes, back-ordered items and decisions changed mid-project. We order long-lead items as soon as you approve them and update your schedule weekly.